What Builders Should Expect From Their Electrician on a Waikato Renovation
Short answer for builders: what you need from an electrical subbie is a firm price, a crew that turns up on the day booked, and pre-wire that does not hold up your linings. Everything else is detail. This is how we work a renovation, written for the person running the programme rather than the person living in the house.
We are based at Waerenga in the North Waikato and work across the Waikato and South Auckland. Registered since 2013, EWRB E 243698.
Where renovation programmes actually slip
In our experience it is rarely the electrical work itself. It is four things, and all four are avoidable.
Scope decided too late. The appliance schedule and the furniture layout drive socket and circuit positions. If those are not settled before pre-wire, either we guess or you wait.
Existing wiring nobody opened up. On a pre-1990 renovation what is in the wall is rarely what is on the plan. Worth an hour of investigation before anyone prices the job.
The switchboard not being in scope. Half of Waikato renovation jobs turn into a board job once you add a kitchen circuit, a bathroom heat pump and an oven. If the board is full, that is a variation nobody budgeted.
Waiting on the lines company. If the mains need upgrading, that is weeks, not days — and it is their timeline, not ours. See which lines company covers your address.
How we fit your programme
Pre-start walk-through. We price off the plan, then walk the site before we commit. That is where the switchboard question gets answered.
Pre-wire in your window. Between roof-on and linings. Tell us the date and we work to it. If we hold that up, we hold up your whole job, and we know it.
Fit-off after painting. Fast, if the pre-wire was right.
Test, certify, done. Certificate of Compliance issued, and a Record of Inspection where the work needs one. Straight to you and the owner, not two weeks later.
What we need from you to price it properly
Plans, and the appliance schedule if there is one.
Whether the existing board and mains are in scope or assumed fine.
Your pre-wire and fit-off dates, even if they are rough.
Who is making the call on variations — you or the owner.
Access and parking, particularly on an occupied renovation.
Give us those and you get a fixed price. Leave the board out and you get a price with an exclusion on it, which helps nobody.
Variations, handled the boring way
Variations on a renovation are normal — the wall opens up and there is something nobody expected. What is not normal is finding out about them on the final invoice. We price variations before doing them and confirm in writing who approved it. It is slower in the moment and much faster at the end.
The bits builders tell us other sparkies get wrong
Turning up on the day. The most common complaint we hear about our trade, and the easiest thing to get right.
Leaving the site tidy. Offcuts and packaging are not the next trade's problem.
Talking to the owner without telling you. If the owner asks us for something extra, it comes back to you first.
Paperwork late. Certificates go out when the job is done, not when someone chases.
Questions builders ask us
Do you work to a preferred subcontractor agreement?
Yes. If you are doing regular volume, a standing arrangement with agreed rates and response times is simpler for both of us than pricing each job cold.
How far do you travel?
Waikato and South Auckland from Waerenga. Te Kauwhata and Huntly are 10 to 15 minutes, Hamilton and Pukekohe 30, Cambridge and Thames closer to an hour. We will tell you honestly if a job is too far to service properly.
Can you do the trenching for a garage or sleepout?
Yes — we have a skilled digger operator on the crew, so an underground run is one quote and one team rather than you coordinating a digger contractor. To be clear on scope, we are not registered drainlayers, so wastewater and stormwater drainage is not ours. See trenching contractor or electrician.
What about a new build rather than a renovation?
Same crew, different sequence. See the new build timeline from slab to sign-off.
Talk to us before the season gets away
Renovation work peaks through spring and summer and the good subbies book out. If you want a sparky lined up for the run to Christmas, call Kris on 021 466 666 now rather than in November. See the renovations page.